Tier 5 (Kwai Chung) data center UPS Installation Project

  • Construction Period: MAR 2022 – DEC 2022
  • The installation of Uninterruptible Power Supply (UPS) systems with lithium batteries is a crucial component of this project. The scope of work includes the storage, delivery, and installation of the UPS units, along with the necessary cabling and connections. To ensure the seamless integration of the UPS systems, our team will conduct comprehensive testing and commissioning, including pre-testing and Site Acceptance Test (SAT). The successful implementation of this project will guarantee the smooth functioning of the data center, allowing it to operate at optimal levels with minimal downtime.